Four laning of chichira-kharagpur section
Project Watch
/
Nov 1 2018
Project Details
Four laning of Chichira to Kharagpur section of NH-6 from km 185.150 to km 134.400 including rehabilitation of existing four lane road from km 134.400 to km 129.600 in the state of West Bengal under NHDP phase IV b on EPC mode.
Name of Authority
National Highways Authority of India
Contractor
Dilip Buildcon Ltd
Project Cost
Rs. 613.08 Crore
Concession Agreement Signing Date
14th October 2016
Date of Commencement
16th March 2017
Constructions Period
910 days (Including maintenance and defect Liability period of 48 months)
Date of Completion
September 2019
Current Status
55 Per Cent work is completed
Contacts
T. K. Baidys, Project Director, PIU-Kharagpur, NHAI Complex, Near Chowrangee,Inda, Kharagpur-721305, West Bengal. T: 0322-2225907, M: 9831563673, kha@nhai.org, piukgp2010@gmail.com
Tags Cloud
Four Laning