Jul 01, 2019 Industry View | Material Handling Equipment | thyssenkrupp Industries We have seen many power projects in the recent past being delayed due to non-performance of Coal Handling package vendors.
May 15, 2016 Construction of residences at ATP Colony Plans to assign the construction of 8 nos.double storeyed Type V residences at ATP Colony, Anpara, Sonebhadra. The completion is targeted in 456 days.
Apr 01, 2015 500 MW unit of Anpara D power plant Setting up 500 MW unit of Anpara D power plant. This will be operational soon. The unit is expected to work on a plant load factor of around 80%. The power generated would be sold to UPPCL at Rs 3.5 per unit.
Aug 15, 2012 Meja Thermal Power Project Bagged a contract from Meja Urja Nigam (a JV between NTPC and UPRVUNL) for supply of ash handling system including transportation, insurance, installation, commissioning and conducting guarantees tests for Meja Thermal Power Project (2x660 MW).