Project Details

Six laning of Kamrej – Chalthan section from Km. 248.100 to Km. 264.350 of NH- 8

including long term remedial measures for 4 Black Spots in Kamrej Bharuch section of NH-8 in the state of Gujarat on EPC Mode.

Name of Authority National Highways Authority of India
Contractor

State Construction Integrated Works of Administrative Department of Verkhona Rada of Ukraine and Unique Construction-Ukraine,rej Bharuch section of NH-8 in the state of Gujarat on EPC Mode.

Project Cost Rs. 241 Crore
Contract Agreement Signing Date June 2016
Date of Commencement 23rd March 2017
Date of Completion 20th March 2019
Current Status 5 per cent work is under progress