Design, construction, development, finance, operation and maintenance of four laning of Panvel to Indapur section of NH-17 from Km. 0+000 to 84+000 in the State of Maharashtra under NHDP Phase-III on DBFOT basis.

Oct 1 2017 | Project Watch

Four Laning of Panvel - Indapur Section

Project Details

Design,construction,development, finance,,operation and maintenance of four laning of Panvel to Indapur section of,NH-17 from Km. 0+000 to 84+000 in the State of Maharashtra under NHDP,Phase-III on DBFOT basis.

Name of Authority
National Highways Authority of India
Concessionaire Supreme Panvel Indapur Tollways Pvt Ltd
Independent Engineer Yongma Engineering Co. Ltd
Project Cost 942.69 Crore
Project Length 84 Km
Concession Agreement Signing Date 21st January 2011
Date of Commencement 19th December 2011
Concession Period 21 years (19th December 2011 to 18th December 2032)
Date of Completion June 2018
Current Status 56% Per cent work is completed
Contacts Prashant Fegade, Project Director, Survey No-63,Chinchpada-Kalamboli Bypass Road, Panvel-410206, Navi Mumbai, Maharashtra.
T: 022-65140560, M: 7738176575, dpiupanvel@nhai.org, piupanvel@gmail.com