Four Laning of Kiratpur to Ner Chowk Section of NH-21 from Km. 73.200 to Km. 186.500 in the state of Punjab and Himachal Pradesh to be executed as BOT (Toll),on DBFOT pattern under NHDP Phase - IV.

Jun 1 2017 | Project Watch

Four Laning of Kiratpur to Ner Chowk Section

Project Details

Four Laning of Kiratpur to Ner Chowk Section of NH-21 from Km. 73.200 to Km. 186.500 in the state of Punjab and Himachal Pradesh to be executed as BOT (Toll),on DBFOT pattern under NHDP Phase - IV.

Name of Authority National Highways Authority of India
Concessionaire Kiratpur Ner Chowk Expressway
Ltd
Independent Engineer Getinsa Ingenieria S.L.Spain
Project Cost Rs. 1818.47 Crore
Concession Agreement Signing Date 16th March, 2012
Date of Commencement 14th November,
2013
Concession Period Concession Period
Date of Completion November 2016
Revised Date of Completion February 2018
Current Status 68.41 Per Cent work
is completed
Contacts Lt Col Yogesh Chandra, Project Director, NHAI, PIU-Mandi, Bagla Muhal Chakkar, PO Nagchala, Tehsil Balh,,Distt Mandi-175021, Himachal Pradesh. T: 01905-246483,,M: 9805960483, pd.mandipiu@gmail.com