Nov 27 2017 | Project Watch

Six laning of Chennai to Tada section

Project Details

Six laning of Chennai to Tada section of NH-5 from km. 11.000 to km,54.400 in the state of Tamil Nadu to be executed as BOT on DBFOT pattern,under NHDP phase V.

Name of Authority National Highways Authority of India
Concessionaire L&T Chennai Tada Tollway Ltd
Independent Engineer SNC-Lavalin International-Aarvee Associates (JV)
Project Cost Rs. 418.75 Crore
Concession Agreement Signing Date 3rd June 2008
Date of Commencement 15 Years (Including 912 days of construction period)
Date of Completion 1st October 2011(27th March 2014 as approved by Executive Committee, NHAI HQ)
Revised Date of
Completion
2018
Current Status 55.655 Per Cent work is completed. Due to land acquisition issues project is in delay mode
Contacts

G.Athipathi,Project Director, NHAI, Project Implementation Unit-Chennai, Sri Towers, 3rd,Floor, DP 34 (SP) Industrial Estate,Guindy,Chennai-600032,Tamil Nadu.T:044-22251885,M:9442527805,chennaipiu@gmail.com