Four laning of Bareilly-Sitapur section

Project Details

Four laning of Bareilly-Sitapur section of NH – 24, from km 262.00 - km 413.200 (Approved Length 157.6 Km) in the State of Uttar Pradesh Under NHDP- III on design, build, finance, operate and transfer (the “DBFOT”) Basis.

Name of Authority National Highways Authority of India
Concessionaire Bareilly Highways Project Ltd
Independent Engineer Intercontinental Consultants &,Technocrats Pvt Ltd
Project Cost Rs. 1046 Crore
Concession,Agreement Signing Date 22nd June 2010
Date of Commencement 1st March 2011
Concession Period 20,Years (Including 910 days construction period)
Date of Completion September 2013
Revised Date of Completion Jan 2018
Current Status 65 Per Cent work is completed