Six laning of Samaikhiali - Gandhidham section of NH-8A from km 306.00 to km362.16 (Length – 56.16 Km) in the state of Gujarat under NHDP Phase III to beexecuted as BOT (TOLL) basis.

Jul 15 2017 | Project Watch

Six laning of Samaikhiali - Gandhidham section

Project Details

Six laning of Samaikhiali - Gandhidham section of NH-8A from km 306.00 to km362.16 (Length – 56.16 Km) in the state of Gujarat under NHDP Phase III to beexecuted as BOT (TOLL) basis.

Nameof Authority National Highways Authority of India
Concessionaire L&T Samakhiyali Gandhidham Tollway Ltd
Independent Engineer Louis Berger Group Inc.
Project Cost Rs.953.88 Crore
Concession Agreement Signing Date 19th March 2010
Date of Commencement 19th Jan 2011
Concession Period 25 Years (Including 910 days construction period)
Date of Completion 16th July 2013
Revised Date of Completion December 2017
Current Status 89 Per Cent work is completed
Contacts Prabhat Kumar Singh, Project Director-PIU, NHAI, Z-6, Ground Floor,Near Divine Life Society Hospital (Sterling), Adipur, Kutch-370205, Gujarat.T: 02836-260104, gan@nhai.org

Advertise Here [728 W x 90 H pixels]