Four laning of Hoskote to Dobbaspet section of NH-2017 from Km 58+300 to Km 138+320 in the state of Karnataka under NHDP Phase IV to be executed as DBFOT (Toll) basis.

Apr 1 2017 | Project Watch

Four laning of Hoskote - Dobbaspet section

Project Details

Four laning of Hoskote to Dobbaspet section of NH-2017 from Km 58+300 to Km 138+320 in the state of Karnataka under NHDP Phase IV to be executed as DBFOT (Toll) basis.

Name of Authority National Highways Authority of India
Concessionaire Transstroy Hoskote-dobbaspet Tollways Pvt Ltd
Independent Engineer Aarvee Associates
Project Cost Rs.720.85 Crore
Concession Agreement Signing Date 30th August 2012
Date of Commencement 05th May 2014
Concession Period 30 Years (Including,910 days of construction period)
Date of Completion 4th May 2016
Revised Date of Completion 31st December 2017
Current Status 7.43 Per Cent work is completed