Design,engineering, finance, construction, operationand maintenance of 4/6 Laning of Trichy to Karur section from km 135.800 (excluding Lalapet ROB) to km 218.028 of NH 67under NHDP phase IIIA on Build, Operate and Transfer (BOT) basis.

Mar 15 2017 | Project Watch

4/6 LANING TRICHY TO KARUR SECTION

Project Details

Design,engineering, finance, construction, operation

and maintenance of 4/6 Laning of Trichy

to Karur section from km 135.800 (excluding Lalapet ROB) to km 218.028 of NH 67under NHDP phase IIIA on Build, Operate and Transfer (BOT) basis

Name of Authority National Highways Authority of India
Concessionaire TK Toll Road Pvt Ltd
Independent Engineer Wilbur Smith Associates Inc. In JV with
Wilbur Smith Associates Pvt. Ltd.
Project Cost Rs. 516 Crore
Concession Agreement Signing Date 19th July 2007
Date of Commencement 15th January 2008
Concession Period 30 Years (15th Jan 2008 to 14th
Jan 2038)
Date of Completion 14th July 2010
Revised Date of Completion June 2018
Current Status 83.62 Per Cent work is completed
Contacts

T V Shvaji, Project,Director, No. 7,

Kamadhenu Nagar, Karur-639001,

Tamil Nadu.,T: 04324 - 223670 , karur@nhai.org