Four laning of Patna-Bakhtiyarpur section of NH-30 from Km. 181+300 to Km. 231+950 in the state of Bihar under NHDP phase III on DBFOT (Toll) Basis.

Jun 1 2015 | Project Watch

Four laning of Patna-Bakhtiyarpur section

Project Details Four laning of Patna-Bakhtiyarpur section of NH-30 from Km. 181+300 to Km. 231+950 in the state of Bihar under NHDP phase III on DBFOT (Toll) Basis.
Name of Authority National Highways Authority of India
Concessionaire Patna-Bakhtiyarpur Tollway Ltd
Independent Engineer Consulting Engineers Group Ltd
Project Cost Rs. 908.02.Crore
Concession Agreement Signing Date 31st March 2011
Date of Commencement 26th September 2011
Concession Period 18 years (Including 910 days of construction period)
Scheduled Date of Completion 24th March 2014
Revised Date of Completion 30th June 2015
Current Status 96 per cent work is completed
Contacts R K Srivastava, Project Director, NHAI, Patna – 800001, Bihar,
T: 0612-2540184, M: 8002733409, patna@nhai.org