Apr 1 2015 | Project Watch

Four laning Maharashtra / Karnataka Border - Sangareddy Section

Project Details Four laning Maharashtra / Karnataka Border - Sangareddy Section of NH-9
(from Km. 348.800 to km. 493.000 of NH-9) in the State of Karnataka and
Andhra Pradesh to be executed as BOT (Toll) project on DBFOT pattern
under NHDP phase III
Name of Authority National Highways Authority of India
Concessionaire L&T Deccan Tollways Ltd
Independent Engineer CDM Smith JV with Willbur Smith
Project Cost Rs. 1266.66 Crore
Concession Agreement Signing Date 2nd February 2012
Date of Commencement 1st April 2014
Concession Period 25 years (Including Construction period 2.5 years)
Scheduled Date of Completion 13th September 2016
Current Status 18.76 per cent work is completed
Contacts PS Dodamani, Project Director, NHAI, Venkatesh Nagar, Gulbarga,
Karnataka. T: 08472-253756, M: 9686495934, piugulbarga@gmal.com